S.N |
Name of work |
Contract ID |
Name of Contractor |
Contract Amount |
Date of Agreement |
Date of completion as per Agreement |
Due Date of Completion |
Time Extended based on Original schedule |
Time Elapsed based on revised schedule |
Financial Progress |
Physical Progress |
Progress Status |
Remarks |
Amount |
Percent |
Date |
Percent |
Date |
1 |
Dyke extension works Ch 10+900 to CH 12+500 |
PBIP/RT/NCB-02/073/74 |
Swochchhanda Nirman Sewa |
87609792.28 |
2017-07-13 |
2019-07-12 |
2020-06-26 |
148.01% |
100.83% |
54275443 |
61.95% |
2020-03-31 |
61.00% |
2020-03-31 |
1 |
Next time extension in process |
2 |
Construction of Canal and Structures |
BIP/MC/NCB/04-2072/73 |
Swochchhanda Nirman Sewa |
270000000 |
2020-03-31 |
2020-03-31 |
2020-03-31 |
171.48% |
101.16% |
237322651 |
87.9% |
2020-03-31 |
87.9% |
2020-03-31 |
1 |
Next time extension in process |
3 |
Banghushree Protection Works |
BIP/RT/NCB-10/075/76 |
Jaya Ma Swargadwari/Jaljala JV |
159900000.00 |
2020-03-31 |
2020-03-31 |
2020-03-31 |
Not extended |
40.47% |
111323198 |
69.6% |
2020-07-18 |
90.00% |
2020-07-18 |
1 |
|
4 |
Construction of Settling basin and protection works |
BIP/ST/NCB/09-2075/76 |
Shree Jayanti Nirman Sewa |
47784606.12 |
2020-03-31 |
2020-03-31 |
|
time not extended |
72.63% |
31835000 |
66.6% |
2020-07-18 |
70.00% |
2020-07-18 |
1 |
Almost on Schedule |