| १ | बड्कापथ पूरा भएको सम्झौता |
|
Name of project
|
Name of work
|
Contract identification number
|
Name and address of contractor
|
Date of agreement
|
Amount of Agreement (Inc VAT/VO)
|
Date of completion
|
Actual Expenditure (inc VAT, price escalation)
|
Contractors liability status
|
Current status
|
Major works completed
|
|
बड्कापथ
|
Construction of core wall and embankment for the protection of Ransing Superpassage
|
BIP/SP/NCB-16/079-80
|
Lokmani/Balarupi/Prabhudev Joint Venture, Ghorahi-15, Dang
|
2023-03-21
|
43,703,257.98
|
2023-11-10
|
43,421,150.59
|
Completed
|
Completed
|
2080/7/24
|
|
बड्कापथ
|
Construction of RCC Lined Canal on Katengaun & Gairagaun Sinchai Kulo
|
BIP/Maintenance/NCB-08/078-79
|
Jana Nirman Sewa, Rolpa
|
2022-03-13
|
1,677,672.85
|
2022-06-29
|
1,844,599
|
Completed
|
Completed
|
2079/03/15
|
|
बड्कापथ
|
Construction of RCC Drain along the Badkapath Main Canal & ramp on Rapti Embankment
|
BIP/Maintenance/NCB-07/078-79
|
Sahadev Nirman Sewa
|
2022-03-14
|
3,513,062.5
|
2022-06-29
|
3,591,465
|
Completed
|
Completed
|
2079/03/15
|
|
बड्कापथ
|
Construction of RCC Lined Canal on Gobahardiya Khaireni Sinchai Kulo
|
BIP/Maintenance/NCB-06/078-79
|
Abhisekh Nirman Sewa
|
2022-03-03
|
3,516,571.6
|
2022-06-29
|
3,669,408
|
Completed
|
Completed
|
3/15/2079
|
|
बड्कापथ
|
Maintenance of Headworks, Protection works and Canal Lining of Dangalichhap and Aatipakhar Kulo System
|
BIP/Maintenance/NCB-05/078-79
|
Birat Nirman Sewa, Lamahi-1, Dang
|
2021-12-31
|
4,265,504.64
|
2023-01-08
|
3,902,322
|
Completed
|
Completed
|
2079/09/24
|
|
बड्कापथ
|
Construction of side drain and RCC canal lining from ch. 5+220 to ch.5+300 and ch. 5+520 to ch.5+770 along the Badkapath main canal
|
BIP/Maintenance/NCB-04/078-79
|
Rapti Nirman Sewa
|
2021-11-10
|
10,785,864.31
|
2023-10-11
|
10,459,939.69
|
Completed
|
Completed
|
2080/06/24
|
|
बड्कापथ
|
Construction of Side Drain, Random Rubble Masonry (RRM) wall, Railing works for the Protection works of Settling Basin
|
BIP/Maintenance/NCB-03/078-79
|
Deurali Engineering Company Pvt. Ltd., Kathmandu
|
2021-11-11
|
3,763,640.91
|
2022-07-08
|
3,663,883.94
|
Completed
|
Completed
|
2079/03/24
|
|
बड्कापथ
|
Construction of cana, concrete side drain at ch 3+100 and gabion Revetment at different Location for Protection of canal bank and Escape at ch.3+300 of Badkapath Main Canal
|
BIP/Maintenance/NCB-02/077/78
|
Rapti Nirman Sewa
|
2021-02-22
|
7,796,332.5
|
2021-06-09
|
7,384,735.11
|
Completed
|
Completed
|
2078/03/25
|
|
बड्कापथ
|
Construction of gabion revetment along with launching apron for protection of the drain & side slope of badkapath main canal at different location
|
BIP/Maintenance/NCB-01/077/78
|
Sunchhari Construction
|
2021-02-24
|
8,079,860
|
2021-06-30
|
8,984,081.00
|
Completed
|
Completed
|
2078/03/25
|
|
बड्कापथ
|
Construction of Bangushree Protection Works
|
BIP/RT/NCB -10/075-76
|
Jaljala-Jayama-Swargadwari JV
|
2019-09-27
|
159,975,085.36
|
2021-09-25
|
160,422,773
|
Completed
|
Completed
|
|
|
Name of project
|
Name of work
|
Contract identification number
|
Name and address of contractor
|
Date of agreement
|
Amount of Agreement (Inc VAT/VO)
|
Date of completion
|
Actual Expenditure (inc VAT, price escalation)
|
Contractors liability status
|
Current status
|
Major works completed
|
|
बड्कापथ
|
Construction of Settling basin and Protection Works at BIP
|
BIP/ST/NCB -09/075-76
|
Shree Jayanti Nirman Sewa, Kathmandu
|
2019-06-30
|
47,784,606.12
|
2020-06-29
|
46,048,337
|
Completed
|
Completed
|
3/15/2077
|
|
बड्कापथ
|
Construction and Maintenance of RT&Canal Structures along the Badkapath main canal
|
BIP/MT/NCB-15/079/080
|
सृजना कन्स्ट्रक्सन, बुटवल ११, रुपन्देही
|
2079-11-26
|
१,८५,९५,०६५/८३
|
2080-03-25
|
|
Completed
|
Completed
|
|
|
बड्कापथ
|
जल उपभोक्ता संस्थाको भवन निर्माण
|
BIP/BLDG/NCB-14/078/079
|
राप्ती निर्माण सेवा काठमाडौँ ३५
|
2078-07-24
|
४७,२२,५९७/१०
|
2079-07-24
|
|
Completed
|
Completed
|
|
|
बड्कापथ
|
चौकीद कवाटर निर्माण
|
BIPMaintenance/NCB-09-078/079
|
सुन छहारी कन्स्टक्सन प्रा.लि. काठमाडौँ ३५
|
2078-11-29
|
१८,०७,३२६/९७
|
2079-05-05
|
|
Completed
|
Completed
|
|
|
Badkapath Irrigation Project
|
Construction of Canal & Canal Structures (CH 4+150 to 7+300, Bhalubang Bridge Crossing and Cross Drainage Works)
|
BIP/MC/NCB-04/072-73
|
Swachhand Nirman Sewa, Kathmandu
|
2016-06-05
|
2,743,212,628.39
|
2020-12-05
|
260,651,840.30
|
Completed
|
Completed
|
Canal from CH 4+150 to 7+300, Bhalubang Bridge Crossing and Cross Drainage Works
|
|
Badkapath Irrigation Project
|
Procurement and Installation of Intake and Escape Gates and accessories of Badkapath Irrigation Project.
|
BIP/GT/NCB-11/075/76
|
MS Shiva Shakti Sakura Power JV Kathmadu
|
2019-09-15
|
26,566,001.09
|
2020-04-11
|
26,565,526
|
Completed
|
Completed
|
Under Defect Liability Period
|
|
Badkapath Irrigation Project
|
Bhalubang Protection works
|
BIP/RT/NCB/05/072-73
|
Waiba Construction company pvt. Ltd., Kathmandu
|
2016-08-16
|
25,366,613.47
|
2018-12-25
|
25,258,436
|
Completed
|
Completed
|
1.0 km long embankment work @ Right side of river near Bhalubang
|
|
Badkapath Irrigation Project
|
Construction of Canal and Structures CH 0+060 to CH 0+450
|
BIP/MC/NCB-08/074/75
|
Lumbini Jaljala JV
|
2017-08-22
|
93,239,102.40
|
2019-07-15
|
95,169,317
|
Completed
|
Completed
|
Main Canal 0+060 to 0+450 with Protection
|
|
Badkapath Irrigation Project
|
Malmala Protection work
|
BIP/RT/NCB-07/073/74
|
Aashish/ Shree Jayanti /Dragon JV
|
2017-07-13
|
78,711,266.44
|
2019-07-15
|
75,047,345
|
Completed
|
Completed
|
Malmala Protection work, 1.5 K.M
|
|
Badkapath Irrigation Project
|
Intake Protection Works
|
BIP/RT/NCB/06/073-74
|
Oasis /Shree Jayanti JV
|
2017-07-13
|
21,917,850.00
|
2018-07-13
|
22,667,499
|
Completed
|
Completed
|
Protection works 240m @ U/S of Intake @Left side of river
|
|
Name of project
|
Name of work
|
Contract identification number
|
Name and address of contractor
|
Date of agreement
|
Amount of Agreement (Inc VAT/VO)
|
Date of completion
|
Actual Expenditure (inc VAT, price escalation)
|
Contractors liability status
|
Current status
|
Major works completed
|
|
Badkapath Irrigation Project
|
Constrution of Canal and Canal Structures
|
BIP/MC/NCB-03/071/72
|
Kumar Shrestha/Ashis Nirman Sewa J./v
|
2015-01-25
|
176,321,414.00
|
2018-07-14
|
179,083,894
|
Completed
|
Completed
|
Main Canal 1+360 to 4+150 with structues
|
|
Badkapath Irrigation Project
|
Constrution of Canal and Canal Structures
|
BIP/MC/NCB-02/071/72
|
Kumar Shrestha Nirman Sewa, Mahendranagar
|
2015-01-25
|
102,613,496.00
|
2019-04-28
|
105,558,830
|
Completed
|
Completed
|
Main Canal 0+450 to 1+360 with structues
|
|
Badkapath Irrigation Project
|
Construction of Side Intake, Barrel and Protection Work
|
BIP/MC/NCB-01/068/69
|
Kalika Pacific JV, Manamohan marga, Kathmandu
|
2016-06-05
|
100,656,219.60
|
2018-06-06
|
92,708,786
|
Completed
|
Completed
|
Intake and canal up to 0+060, Intake Protection works
|
| २०८०-०३-२५ | — |