सम्झौता प्रगति
Contract Progress
|
S.N |
Name of work |
Contract ID |
Name of Contractor |
Contract Amount |
Date of Agreement |
Date of completion as per Agreement |
Due Date of Completion |
Time Extended based on Original schedule |
Time Elapsed based on revised schedule |
Financial Progress |
Physical Progress |
Progress Status |
Remarks |
|||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Amount |
Percent |
Date |
Percent |
Date |
||||||||||||
|
1 |
Construction of Canal and associated structures from ch.7+300 to 9+000 along Badkapath Main Canal |
BIP/MC/NCB -12/077-79 |
Kankai/Karna J.V., Tokha-6, Kathamandu |
149382060.71 |
2021-04-12 |
2024-10-15 |
1 |
|||||||||
|
2 |
Construction of Canal and associated structures from ch.9+000 to 14+450 along Badkapath Main Canal |
BIP/MC/NCB -13/077-78 |
Kalika/Bandan Bhagwati/Buddha Himali JV, Baluwatar, Kathmandu |
780077282.08 |
2021-04-12 |
2026-04-13 |
1 |
|||||||||
|
3 |
Canal lining, drain, related structure and protection work along Badkapath Main Canal, Ch.6+765.25 to Ch7+372.25 |
BIP/MC/NCB-17/079-80 |
Mallarani-K.B.Joint Venture, Pyuthan |
46664625.09 |
2023-07-02 |
2024-06-29 |
63 |
70 |
1 |
|||||||
|
S.N |
Name of work |
Contract ID |
Name of Contractor |
Contract Amount |
Date of Agreement |
Date of completion as per Agreement |
Due Date of Completion |
Time Extended based on Original schedule |
Time Elapsed based on revised schedule |
Financial Progress |
Physical Progress |
Progress Status |
Remarks |
|||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Amount |
Percent |
Date |
Percent |
Date |
||||||||||||
|
1 |
Dyke extension works Ch 10+900 to CH 12+500 |
PBIP/RT/NCB-02/073/74 |
Swochchhanda Nirman Sewa |
87609792.28 |
2017-07-13 |
2019-07-12 |
2020-06-26 |
148.01% |
100.83% |
54275443 |
61.95% |
2020-03-31 |
61.00% |
2020-03-31 |
1 |
Next time extension in process |
|
2 |
Construction of Canal and Structures |
BIP/MC/NCB/04-2072/73 |
Swochchhanda Nirman Sewa |
270000000 |
2020-03-31 |
2020-03-31 |
2020-03-31 |
171.48% |
101.16% |
237322651 |
87.9% |
2020-03-31 |
87.9% |
2020-03-31 |
1 |
Next time extension in process |
|
3 |
Banghushree Protection Works |
BIP/RT/NCB-10/075/76 |
Jaya Ma Swargadwari/Jaljala JV |
159900000.00 |
2020-03-31 |
2020-03-31 |
2020-03-31 |
Not extended |
40.47% |
111323198 |
69.6% |
2020-07-18 |
90.00% |
2020-07-18 |
1 |
|
|
4 |
Construction of Settling basin and protection works |
BIP/ST/NCB/09-2075/76 |
Shree Jayanti Nirman Sewa |
47784606.12 |
2020-03-31 |
2020-03-31 |
time not extended |
72.63% |
31835000 |
66.6% |
2020-07-18 |
70.00% |
2020-07-18 |
1 |
Almost on Schedule |
|