Name of project
Name of work
Contract identification number
Contractor's Name & address
Agreement Date
Amount of Agreement (Inc VAT/VO)
Date of completion as per agreement
Number of extension
Total duration of time extension (months)
Date of completion (revised)
Current status
Updated Progress
Responsible person
बड्कापथ
Canal lining, drain, related structure and protection work along Badkapath main canal ch. 6+765.25 to 7+372.25
BIP/MC/NCB-17/079/081
मल्लरानी-के.बि. जे.भी. खलगा, प्यूठान
2080-03-17
४,६६,६४,६२५/०९
2081-03-16
Ongoing
100%
Ashwin Raut
Badkapath Irrigation Project
Construction of Canal and associated structures from Ch.9+000 to Ch.14+450 along Badkapath Main Canal
BIP/MC/NCB-13/077-78
Kalika/Bandan Bhagwati/Buddha Himali JV, Baluwatar, Kathmandu
2021-04-13
780,077,282.08
2026-04-13
24%
Vijay Roka
Construction of Canal and associated structures from Ch.7+300 to Ch.9+000 along Badkapath Main Canal
BIP/MC/NCB-12/077-78
Kakai/Karna JV, Tokha-06, Kathmandu
2021-04-12
149,382,060.71
2023-04-12
76.83%
Nabin Gurung
Banghushree Protection work
BIP/RT/NCB-10/075/76
Jaljala/Jayama Sworgadwari JV, Kathmandu
2019-09-27
159,975,085.36
2021-09-26
Amount: 157,977,059.19, Phys: 99%, Fin: 99%
Keshav Kandel
Construction of Settling Basin and Protection Works
BIP/ST/NCB-09/075/76
Shree Jayanti Nirman Sewa, Kathmandu
2019-07-16
47,784,606.12
2020-12-15
Amount: 31,835,000, Phys: 70%, Fin: 67%
Belman Budhamagar