नेपाल सरकारऊर्जा, जलस्रोत तथा सिँचाइ मन्त्रालयजलस्रोत तथा सिँचाइ विभाग
लमही-५, दाङ
Contract Progress
S.N
Name of work
Contract ID
Name of Contractor
Contract Amount
Date of Agreement
Date of completion as per Agreement
Due Date of Completion
Time Extended based on Original schedule
Time Elapsed based on revised schedule
Financial Progress
Physical Progress
Progress Status
Remarks
Amount
Percent
Date
1
Construction of Canal and associated structures from ch.7+300 to 9+000 along Badkapath Main Canal
BIP/MC/NCB -12/077-79
Kankai/Karna J.V., Tokha-6, Kathamandu
149382060.71
2021-04-12
2024-10-15
2
Construction of Canal and associated structures from ch.9+000 to 14+450 along Badkapath Main Canal
BIP/MC/NCB -13/077-78
Kalika/Bandan Bhagwati/Buddha Himali JV, Baluwatar, Kathmandu
780077282.08
2026-04-13
3
Canal lining, drain, related structure and protection work along Badkapath Main Canal, Ch.6+765.25 to Ch7+372.25
BIP/MC/NCB-17/079-80
Mallarani-K.B.Joint Venture, Pyuthan
46664625.09
2023-07-02
2024-06-29
63
70
Dyke extension works Ch 10+900 to CH 12+500
PBIP/RT/NCB-02/073/74
Swochchhanda Nirman Sewa
87609792.28
2017-07-13
2019-07-12
2020-06-26
148.01%
100.83%
54275443
61.95%
2020-03-31
61.00%
Next time extension in process
Construction of Canal and Structures
BIP/MC/NCB/04-2072/73
270000000
171.48%
101.16%
237322651
87.9%
Banghushree Protection Works
BIP/RT/NCB-10/075/76
Jaya Ma Swargadwari/Jaljala JV
159900000.00
Not extended
40.47%
111323198
69.6%
2020-07-18
90.00%
4
Construction of Settling basin and protection works
BIP/ST/NCB/09-2075/76
Shree Jayanti Nirman Sewa
47784606.12
time not extended
72.63%
31835000
66.6%
70.00%
Almost on Schedule